MRP planning improved delivery date

Former Member
0 Kudos

Hello you all,

I have a question regarding the MRP planning of improved delivery dates. Let me schedule the scenario.

As material is ordered, the expected delivey date is indicated by delivery rules. If for some reason the supplier can deliver earlier, this is mentioned in the PO tab Confrmations confirmation catagory AB.

As we run the MRP via transaction V_V2, the updated delivery date is not shown in MD04.

What do i need to do to see the correct data in MD04?

If this is all a bit fuzzy, please ask for further details. I am not a SD consultant.

Thanks in advance for your reply.

Best Regards,

Peter Lans

Accepted Solutions (0)

Answers (1)

Answers (1)

Shiva_Ram
Active Contributor
0 Kudos

Hi,

Run the program SDRQCR21 in SA38.

This will correct the data in MD04.

Hope this helps.