MRP planning improved delivery date

Hello you all,

I have a question regarding the MRP planning of improved delivery dates. Let me schedule the scenario.

As material is ordered, the expected delivey date is indicated by delivery rules. If for some reason the supplier can deliver earlier, this is mentioned in the PO tab Confrmations confirmation catagory AB.

As we run the MRP via transaction V_V2, the updated delivery date is not shown in MD04.

What do i need to do to see the correct data in MD04?

If this is all a bit fuzzy, please ask for further details. I am not a SD consultant.

Thanks in advance for your reply.

Best Regards,

Peter Lans

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jan 31, 2008 at 02:18 PM

    Hi,

    Run the program SDRQCR21 in SA38.

    This will correct the data in MD04.

    Hope this helps.

    Regards

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.