System is creating 2 production orders for single sale orders

when sale order is released then the system is creating 2 production orders as per the ATP check,

ex: A is header and B is component,

as per BOM , 1 EA of A required 1 EA of B,

current stock of B is 30,

user has created Sale order for A with 100 , then system has created 2 production orders with 30 to day & 70 after 10 days , Procurement time for B is 10 days,

user is asking for single production order of A with 100 quantity when the full stock of B is available to full fill the sale order . it means production order of A with 100 quantity.

client is using Z strategy , I hope this is copy of strategy 82,

could you please help me to resolve the issue