Can anybody tell me can we create a production order with routing but without BOM?iS IT POSSIBLE

tHANKS IN ADVANCE

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 12:14 PM

    Hi Laxmikant

    Please note the steps

    Create a BOM Application in OS30

    Create a new BOM ID in OS31 with BOM Usage as Production

    Assign this BOM ID in BOM Application

    Ensure that ID is responsible for Production planning alone.

    Then in that ID maintain a BOM alone without any items.

    Assign this BOM Application in Order type dependent parameters in OPL8

    Now u can create a production order w/o BOM

    Rgds

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 11:21 AM

    HI,

    It is possible. User transaction CO07- create production order without material.

    Regards,

    Krishna Mohan

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 31, 2008 at 11:22 AM

    Hi Lakshmikanth,

    Yes..U can create a production order with routing & without a BOM..But system will log a error entry for master data reading..Ans also while creating the order system gives u a option for exploring a different materials BOM...

    Anyhow u can ignore these messages & still create a production order.

    Thanks & regards

    Mahesh

    Reward points if useful

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 11:24 AM

    Hi,

    you can create production order without BOM

    pls refer below link

    production-order-with-out-bom

    Regards,

    Sankaran

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 11:25 AM

    Hi Laxmikanth,

    It is possible to create a production order for a material with out a BOM. You can enter the components in the order itself if you want.

    Regards

    Krishna

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 11:44 AM

    Hi,

    If u don't want to use BOM that means U don't have any BOM components.

    So don't give any component in cs01

    and save it.

    Ex. : When u producing any gas from air that means u don't have any component so we can use this type of BOM.

    I think this will help u.

    Nilesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.