Hi,

I have inherited and am in the process of reverse engineering some C4C ERP iflows.

I can see via monitor view that there is a deployed and started iflow called

Custom BP Relationship replication from SAP C4C to S4 HANA_TRG however I cannot find any way to stop this.

Grateful for any detailed steps on the process for stopping iflows.

I am aware that I can delete some iflows via design>open package>select relevant iflow>edit>delete as per below however not all are available.

I therefore need a way to stop then restart non-standard (custom) iflows.

Any advice much appreciated

Iain

1.png (32.8 kB)
2.png (18.2 kB)
2.png (18.2 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 15, 2017 at 05:00 PM

    Hi,

    In CPI there is no option to manually start /stop the iflow. The only way to stop the iflow running is to undeploy it.

    Br,

    Manoj

    Add comment
    10|10000 characters needed characters exceeded

    • Thanks again Manoj

      As per the image 1 attached, the default download file type is .jar. I have tried both manually changing this to .zip at point of download and converting to zip afterwards

      3.png

      However on attempting import as per image 2 attached


      4.png

      In both cases the file cannot be imported with error

      "Could not import file: select a valid content package"

      Can you confirm if any additional steps are required to re-import the iflow?

      Regards

      Iain