external operation

hi all,

if i perform one operation in subcontracting how can i define a workcenter for external operation.and how the cost is collected for this operation

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 07:16 AM

    Hi

    To per fo m an operation externally, you have to use control key which will allow externa operation.

    While using this work center in routing , system will prompt you to give purhasing data.

    while creating production order at the time of release , PR will get gebnerated.

    Then MM will take care of this.

    Cost will be cost of the subcontracting will be directly posted to order.

    Hope it is clear.

    Regards

    YMREDDY

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      When the operation is carried out externally it means that we do not have a physical control on the operation, which is carried out at the Subcontractor. So we do not need to maintain that work center.

      We have a control only to mention the operation is external which creates a PO.

      Speaking logically once the material is sent outside the plant for processing, we do not have the physical control of it until we receive the processed component.

      Hope this clarifies you.

  • author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 07:20 AM

    Hi,

    when an operation is performed as external operation, it should have control key related to external processing(standard control key PP02)

    once you attach this control key to any operation, you have to maintain data like Purchase info record( if you maintain cost in that), purchasing group, etc. If you are not maintaining purchase info record, you can enter price directly against that operation in external processing tab.

    PR gets created when the production order is created and you have to process the PR to get Costs assigned to that Production order. .

    Regards,

    Krishna Mohan

    Edited by: Krishna Mohan N on Jan 31, 2008 12:50 PM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 07:40 AM

    Hi,

    Create an operation with the control key having external operation. You need not assign a work center to it. Or you can have a dummy work center without costing ,.. etc.

    Regards

    Krishna

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.