we have book consumption of a material A which is define in bom now bom has been change Material A replace by Material B.

good issue for A material mvt type 261,now my company want to transfer this issue material A repalce by material B,so that system show 261 for material B .

Is there any mvt type to do?

Any suggestion....

shakir

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Jan 31, 2008 at 07:26 AM

    Hi Shakir,

    What was the real consumption? Did you consume materialA or materialB?

    If your production consumed materialB but materialA was withrawn because of the old BOM, you have several option to correct this mistake.

    In CO13 you can cancel the wrong confirmation and do a new one - in this case you have to correct the component list of your PrdOrd in CO02 (F6 - Component overview), or you can do the correction in CO15 in goods movement. (you have to delete materialA and add materialB)

    Other option is to use MB1A with refernce to PrdOrd: you can reverse the withdrawal of materialA via MVT 262 and you can book materialB via MVT 261.

    If you use WM (and dynamic bins) you have to create TR for material staging via LB01 (or in case you correct the PrdOrd you can carry out material staging in CO02)

    BR

    Csaba

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Shakir,

      You can correct the consumptions as it was written above:

      1.

      Cancel all related confirmations (CO13) > correct the component list of the PrdOrd > confirm the quantities with proper consumptions (it can occure that you do not have stock of FGs/SFGs and you cannot carry out the cancellation > in this case you can 'create' stock by MB1A 202 and after having executed the cancellation-confirmation process you have to vanish the stock by MB1A 201)

      2.

      You can realize the proper consumption w/o cancellation:

      MB1A 262 materialA + PrdOrd reference > reverse the withdrawal of materialA

      MB1A 261 materialB + PrdOrd reference > consumption of materialB for each PrdOrd

      3.

      This is the easiest to do but isn't very accurate:

      MB1A 202 + materialA

      MB1A 201 + materialB

      In this case you cannot link these movements to PrdOrds...I recommend that you should do option 1 (maybe the 'best') or option 2...or if somebody can say some better solution to you...

      BR

      Csaba

  • author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 06:26 AM

    Hi,

    What is ur actual requirement. You mean want to tranfer the Stcok of Material A to Material B?

    Thanks

    Raju

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 07:40 AM

    mvt 261 - It is reservation against material through work order.

    Please check in Reservation list MB25

    Regards

    Ravi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.