Dear SAP Gurus,

In Make to Order Scenario, Plant1 is Process Plant and Plant 2 is Sales Plant.

Actually Customer place the order from Plant2, Material require Sales BOM, how do we transfer the stock from Plant1 to Plant2.

In Plant2 client only maintain Finished Goods.

do we have to maintain the BOM componets in Plant2 also.

very urgent,

thanks in advance,

Sathya..............

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 31, 2008 at 06:39 AM

    Hi Sathya,

    1.You are telling that sales BOM is required and sales is happening in the plant 2, so you need to main tain the sales BOM in the plant 2 only.

    2. You are manufacturing at Plant 1 then you are sending the goods to the plant2 through STO right,here maintaining the BOM depends upon you, If you are sending the material as components to plant2 there is no need of BOM,or If you are planning to send the material with the combination of components then you require BOM same as Plant2

    I hope it will help you

    Thanks,

    Murali.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.