what is the PP Master data to be uploaded in to SAP system at the time of implementation?

What are the PP general configuration settings for an industry with only Final Assembling (with out any in-house production)the semi finished products(from sub-contracting vendor) and some spares, in to Finished Product to be delivered to the customer in MTS ( monthly planning) scenario.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Balaji,

The various PP realted master data which has to be collected are

1. BOM / Master Recipe.

2. Routing / Rate Routing.

3. Production Version.

4. Work Centre / Resource.

The configuration settings would depend on the clinet requirement.

Reward if useful.

Narendra

Answers (1)

Answers (1)

Former Member
0 Kudos

HI,

1. Material master related data for MRP views

2. BOM data

3. Work centers data

4. Routings data

5. Production versions(if req)

Regards,