on 01-30-2008 2:59 PM
Hello,
In infostructures S021, S022, S023 and S024 the time unit field DFZEH is set to DAY as SAP standard.
In IMG tc MCRG it seems to be possible to change this time unit which should be useful for short lead times and execution times(field MCPPCUST-DFZEH). Coincidence that field names are the same?
After running statistical update of S023 the unit is still DAY.
I don't see anything in the front end standard analysis that it is possible to change time unit. (This is possible for currency.)
I have tried different options but nothing gives me a result that I expect.
Does somebody know the effects of this IMG setting??
Thank you!
Best regards,
Tor Holter
Oslo, Norway
In LIS there are fields available for the exact times but those fields are not present in the standard Inforstructure. The solution is to create new ones (it is not possible to copy certain infostructure).
These fields are part of BW/BI extract.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.