Planning strategy 20 not available in SAP S/4 HANA

former_member184574
Active Contributor
0 Kudos

Hi

I am implementing S/4 HANA in a manufacturing company. They have a scenario of Make to order production with out variant configuration. So I want to use Pure make to order 20 strategy. This strategy not available in S/4 HANA it seems. Please check the below screen shot. Can you confirm is this strategy removed in HANA. If yes what strategy I can Use.

Thanks

Kumar

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

No, the planning strategy 20 is not removed from S/4 Hana. Please check below screenshot from S/4 Hana 1610 system, its available.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

I also see strategy 20 in my S/4HANA system and I suppose that this is a problem in your system.

Check if this strategy exists in client 000 or try to copy the settings from another system.