on 01-30-2008 9:32 AM
Hi SAP Gurus,
When we do MRP run through MD02,the screen shows material list as per BOM,Exceptional message,Plan stock ect.
If we create indepedent requirement of 25 qty through MD61,while doing MRP Run can it show the following in *one screen-
1 Plant Stock
2 Required qty(Newly Created
3 How much qty I can make with available stock.
4 When will be the Raw material available after planning.
RESULT WILL BE IN ONE SCREEN.
Plz Help.
It is Customer requirement
Regds
Mukesh
it depends on what strategy u define for the header item. whether u want to consume the stock or produce for a particular sales order.
u can see all the updates of mrp run in stock requirement list. this is what i understood from ur question.
sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mukesh Bafana,
It is showing on one screen after MRP run go T code MD04 here you give your main material i.e. Finish Material where you get all this and there is one tab of Show overview tree where you get all BOM list and also as per MRP segment i.e. as per link to this plan order there is depended requirement is generated by system.
Hope this will help you And reward Point.
Regards,
Rajesh Tayade
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.