Hi SAP Gurus,

I have 3 VTL M/Cs.Out of them 2 were complitly dedicated for Turning operation of job A.

If I want to produce 20 jobs,then 10 -10 were distributed on each m/c.

So how can I show it in Routing?

PLz Guide.

Regds.

Mukesh.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can create one work center and put no. of individual capacity as 2 and

use splits in Routing.

Former Member
0 Kudos

Hi,

Thanks for reply.

Can u give the Details Plz.