How to see estemated time in db12.......

Hi every one,

How can i see the estemated time and how much data get backup from the db12 transaction? the backup is in progress....

thanks

Reddy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jan 30, 2008 at 08:06 AM

    Hi Bupathi,

    I dont think you can see the estimated time in DB12.

    It is used to see when the backup has been taken and what was the time taken for the last backup.I think you can assume the same time that would take for the next backup.

    Also using DB12 you can find the drives which will be used

    during a recovery.

    Reward points if helpfull.

    Regards,

    Vamshi.

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 30, 2008 at 09:51 AM

    Hi bhupathi,

    At DB12 click in Last successfull backup -> Detail Log -> You can see at the start of the log the starting time and the ending time at the end of the log, then just calculate how long it took 😉 ; then also in the log... you'll see a line like this "BR0061I (XXX) files found for backup, total size (XXXXXXXXX) MB... thats the size of the files to be backed up.

    Regards

    Juan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 30, 2008 at 06:49 PM

    Hi Bhupathi,

    If you are using the brbackup for backig up your database then in DB14 you can see the estimated time for completion of backup.

    Best Wishes.