Hi Experts....

I have created Holiday calender for the year 2008 and successfully tranported to production server.What are the further things to be done to get complteness...

Please advice....

Regards,

Sai.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 30, 2008 at 06:38 AM

    Next thing is you have to generate all the work schedules

    use Tcode PT01 to generate workschedules

    or use OG00 to generate more no of work schedules

    YOu can do this in develpment and move the changes to produciton

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      thats all.

      it is advisable to run RPTUPD00

      Revaluation of Attendance/Absence Records using Batch Input

      The program creates a batch input session for revaluating absence and attendance records. A revaluation can be necessary if work schedule data on which the valuation is based changes after the absence or attendance is entered, for example.

      The relevant absence or attendance records are saved when the batch input session is processed, and the absence or attendance data is revaluated.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.