Order Types

Order type in cas of REM is "PE" which i can't convert to production order.....thats fine

But many times i get confused when i see order types in MD04 as "RS"..

What is the difference between these "PE" & "RS"...& why sometimes RS comes and sometimes PE...I m bit confused between two

Also i want to know when do we get order type "LA"??

Please comment

Rgds

Edited by: Vicky Khabrani on Jan 30, 2008 5:23 AM

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 30, 2008 at 04:28 AM

    Hi, Vicky.

    As i know RS Indicates - Run scheduler type MRp element which is created when u activate rem mfg idicator at mrp View & production version of palnning material. which results MRP create PE type run scheduler (Planned order).

    Other wise LA - stock order type planned order will be created.

    Regards

    Pradeep

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.