Budget Check

Dear All,

Q1)Can anybody pl let me know if i select option 2 in tolerance limits where i mention at 90% mail to the person responsible

Where the settings can be made.what are the basic configuration to be done.

Q2)If I dont assign any budget in the project still the system is accepting the actual cost,where there is Rs 0 in my budget.

What are the configuration to be made

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 30, 2008 at 02:28 AM

    You need to configure your budget profile first.

    Set the Activation type in the availability control i.e., when this should be activated again on overall budget,relased budget etc.,

    Assign this budget profile to the project profile. T Code OPS9

    Set the Tolerance limits for the budget profile. T Code OPSA Controlling Tab

    Mention the Responsible person on the WBS. T Code CJ20N etc.,

    To stop actuals onto the WBS till you do budgeting you can use user status management. I've explained this in a post recently and below is the link to the thread.

    project-purchase-order

    Regards

    Sreenivas

    Pls close this post if satisfied.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.