CK11N-urgent

Dear all,

While running CK11N, all the activity type costs are not getting calculated, i.e., setup, machine, labour. Can anybody tell why they are not calculating?

Please guide me.

Will award good points.

Regards,

A.Anandarajan.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 29, 2008 at 02:39 PM

    Hello,

    i think that you had to look that the Activities/prices are planed in the right version and the right year were the calculation refers to.

    Use TC: KP27 to look or TC: KP26 to change

    Use TC: KP97 or KP98 to copy

    best regards

    Hans

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 29, 2008 at 02:49 PM

    Hai,

    1. Once see the cost element that is given in the activity type, is mentioned in the cost component structure as production costs

    2. Check in KP26 whether the plan costs for the activity type and cost center are maintained

    With regards,

    Deepa

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      hai,

      As you said, i checked in the cost component strucutre and the cost elements that are given in the activity types are maintained in the cost component structure. And also in kp27, plan costs for the activity type and cost center are given.

      Can you please give where the error would be?

      Will award good points.

      Thanks & Regards,

      A.Anandarajan

  • author's profile photo Former Member
    Former Member
    Posted on Jan 30, 2008 at 05:11 AM

    Hi

    Check wheather your Activity type is assigned in work center or not (CS02).

    Regards

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.