on 01-29-2008 5:15 AM
Hii experts,
Can we have planned cost in REM? If yes, how?
regards
kapil
Dear Kapil,
After doing Production confirmation in MFBF you will be able to
see the Target Costs And Actual Cost in the Product Cost
Collector in KKF6N .
Before doing production confirmation (or never MFBF is carried
out) for a HALB or FERT material ,then in T code KKF6N ---
>Header -
> Click on Costs ,You can not find any data.
So unless if production confirmation is not carried out,you
cannot find the target costs.
Target Cost are the Planned Costs
Regards
Mangal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kapil,
For your Understanding
1.Target costs are the planned costs adjusted to the actual
operating rate.Target costs can be used for purposes such as:
To determine variances
To valuate work in process
To valuate unplanned scrap
2.The Target cost will be your Planned Cost which you have
used during Cost Rollup---this generally given for Raw Materials.
3.The actual Cost will be the price of the consumption that has
happened for 261 moevment materials.
4.Moving average Price of your Raw materials gets varied as
per the GR & its value,So whenever production confirmation is
done for the HALB or FERT materials,you can see the actual
cost getting varied for your RAW materials.
5.So Variance will be of +ve value if Actual Costs is greater
than Target Costs & variance will be - ve Value if Target Costs
is greated than Actual Costs.
6.So during Period end closing as per the Business
requirements varinace is calculated,then settled against some
Cost Objects.
7.For the Items which were not present in the BOM of a HALB
or FERT item during Cost rollup and later on added,for these
items you can see the Target cost will be Zero and only actual
costs field gets updated.
I hope this will be sufficient to get a better understanding.
Revert back in case of any queries.
Regards
Mangalraj
Thanks so very much for your reply sir. I have got a bit idea about this. Another question, I am having in my mind. What if I frequently backflush for particular material, then every time I need to settle the cost. Please suggest when we should settle the cost in case of REM.
I can see COST SETTLE option in KKF6N.
kapil
As I know, you can define planned cost in product cost collector for REM. To define it, you must set up product cost structure.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.