Moving Average Price Updation

Former Member
0 Kudos

Hello Friends,

When we Purcahse materials for Project Stock "Q" during goods recepit the MAP is not getting Updated/Recalculated.Because of this when we do the planning for this material it takes the value in MM manually entered,it may be even Zero "0" price also.

How we can make the settings such that the MAP gets calculated for Project stock "Q" stock also.

Thanks,

RamananPV

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Ramanan,

'Q' stock materials constitute a separate stock segment, distinct from plant stock. This will not update moving average price of plant stock materials which are in a different segment. Hence when you create a PR in new project, prices are taken from the materil master at the plant level.

If you are making multiple procurement of the same material component for the same project segment, perhaps, you will see the updation in that stock segment.

Hope I have got your problem correctly and my understanding is ok.

Muraleedharan.R