Dear SAP Experts,

My client has hot three Profit Centers in One Plant,

Most of the Common Materials are used across profit centers,

He has implemented ECC6, They are using Profit center wise

Balance sheet.

Problem is Profit center is derived from Material Master and and not from the WBS element which is assigned to Purchase Order and Material.

Can some body give me hint to derive profit center from WBS instead of Material Master,

We have tested 2 Scenarios:-

1st Scenario:

We have removed Profit center from Material Master and assigned only in WBS element,

In this case system is deriving default profit center insted of WBS element.

2nd Scenario:

We have incorporated one profit center in Material Master and

different in WBS element.

In this case system puts the profit center from material master at the Time of MIGO and Put Profit center of WBS at the time of Issue posting.

Can somebody suggest,

regards