One report to check status of project/wbs(TECO/REL)+ available budget

Former Member
0 Kudos

Dear All,

Please advice. Is there any report (one for all ) which can show Status of project/wbs + available budget of a project. I tried cns43, cn41 and report s_alr. But it shows in different tcode/report. Hopefully there is a standard report that can show these in one report.

Many thanks in advance.

Nies

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Standard Report CN41 - Structure Overview itself can show the values you are looking for.

After executing the report to include the fields press F5, from the fields available on right hand transfer/choose fields Status and Budget.

Regards

Sreenivas

Pls close the post if satisfied.

Former Member
0 Kudos

Hi Sreenivas,

Appreciate for your advice. However, CN41 shows original budget not the available budget/unused budget. Do you have another idea?

Thank you.

Nies

Former Member
0 Kudos

CN41 shows the Current Budget and not Original Budget.

If Available Budget in your terms means difference between Current Budget and Actual, you can include a column 'Difference' from menu.

Select the Column Budget 1st, Menu Edit>Comparison> Choose Actual Cost.

The output shows the difference and percentage. Problem now is you can't view the status.I can't think of anything standard which exactly gives the ouput columns you are expecting.

Regards

Sreenivas