Dear All,

How can the status of a maintenance order (PM02) be changed back to CRTD from REL.

Regards

Suhail

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 28, 2008 at 05:04 AM

    Hi,

    Status "Release" cannot be reverted to "CRTD" for any cost object as "confirmation", "purchase order" might have been already issued for the object in the "REL' status.

    Muraleedharan.R

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 28, 2008 at 03:40 AM

    hi

    up to my knowledge i think you cannot revert the Release indicator for PM orders

    regards

    thyagarajan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 28, 2008 at 08:58 AM

    Hi,

    As Said by our friends its not possible to change the Release indicated for PM orders

    Regards

    Satish

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.