Hi All,

I have a question relating to SAP solution for a business process which involves 3rd party logistics handling, not sure if this is the correct forum to post this, but if anyone has implemented this scenario, can you please guide me:

Scenario:

The vendors supplying parts to our plant are located in different countries & hence we have outsourced the logistics to a 3rd party. In our earlier implementation the vendors themselves managed the logistics & hence we had a 2 step confirmation i.e. Order Acknowledgment & ASN. But now with the 3rd party logistics handler, we need to add one more confirmation key.

We are using ICH. So if anyone has implemented a solution for a similar scenario, can you please advice. I went thru' SAP ICH help file & it mentions Transportation Lane in APO, can someone advice me what is it?

Await inputs.

Vivek

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 28, 2008 at 10:42 AM

    Hi Vivek,

    Transportation lane in APO:

    Transportation lanes control the material flow along the supply chain.

    Defines the transportation method, ie., means of transport( might be Truck, Plane, Ship etc )

    Also determines the transportation cost, transportation capacity by volume, weight etc.

    Defines the transportation cost per unit, product and transportation methid.

    You can find the scheduling aggrements that you had created in R/3, the planned delivery time etc..

    Path to create transportation lane:

    SAP menu->APO->Master Data->Transportation lane->Transportation lane

    or Transaction: /SAPAPO/SCC_TL1

    reward points if you found it useful...

    Regards,

    Rajendra.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Mr. Rajendra,

      Thanks for your valuable inputs. But i would like to know how can i set up my requirement in ICH? At the moment there is only 2 confirmations & both are done by the vendor. How can i integrate the logistics company in this flow, so they can create the 3rd confirmation for us?

      Hope my question is clear. If anyone has worked or implemented a similar scenario, can you please advice?

      Vivek

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.