planned to production order in MD04

HI,

I am using rem. mfg . given demand and taken MRP run.

Now in MD04 screen , i am getting planned order.

if i double click on that planned order , information screen cum, but here i am not getting that option of directly conversion of planned order to production order.

Why???

Is there any setting for this direct option.

help me...

tahnks

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 26, 2008 at 07:30 AM

    Hi,

    In REM, The planned order itself authorises the production. There is no need to create a production order.

    Regards,

    Santanu

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 26, 2008 at 07:46 AM

    Hi,

    In REM MFG u cannot convert the planned order to production order. Since because PE type planned order & REM is period based production not lot based.

    u can do the production confirmation for planned order directly via MFBF. Now goods movement will happen.

    Regards

    pradeep

    Edited by: Pradeep Kumar on Jan 26, 2008 1:16 PM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.