Hi,

I know in APO, pegging process is existing and is this available in R/3? What am looking is , there FG item with 2 level of BOM

1-primary process-first process

2 -décor process-second process

And finally FG is packed ,-3rd process

Currently if there is any changes is happening in first process , we will have to manually change the PO’s of the process 2 &3 .

With pegging I believe system can automatically change the date of remaining process, is it possible to get it done in R/3 as well?

Thanks to support

Vijesh