Weekly Bucket question

Good morning,

I have an MRP lot size that is a weekly period.

It is set to start at the begining of the period.

I would expect this to be a Monday but it is raising the Procurement Proposals on a Tuesday, what needs to be maintained to work on a Monday.

Thanks

Guy.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Jan 25, 2008 at 09:53 AM

    Hi Guy,

    I guess....

    For example your requirement for a week is 100 Kg and the lead time is 4 days...

    & ur lotsizing procedure is Requorement date = period start & period = week.

    System will ensure that the material should be delivered on the first day of the week ( monday).

    taking consideration of the lead time system creates the planned order/purc reqn start date as the previous Tues day.

    Please come back... If I haven't understood your query correctly.

    Thanks & regards

    Mahesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 25, 2008 at 09:18 AM

    Mr.Hall

    Please understand, weekly period of MRP lot size is just a lot sizing procedure. To create requirements on monday is something related to MRP run and your MRP run is populated by different parameters.

    For starting of week by monday, you can check your factory calender. But we would be able to help you more, if you will ask in precise way.

    cheers!!!!

    kapil

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 25, 2008 at 09:57 AM

    Good morning,

    Thanks for the reply,

    The Factory Calendar is set to 24/7,

    We are using a weekly lot size (with the Procurement being created at the beginning of the period),

    We are running MRP every day NETPL.

    We have changes 10 materials with the Weekly bucket settings and have found the following: -

    6 of the Materials now have the Planning time fence on the Monday and a schedule line created on the same day.

    4 of the Materials now have the Planning time fence on a Tuesday and the schedule line created on the same day.

    We are not using any Planning calendars.

    I am confused why we are getting the required results on the first 6 but not the last 4.

    I have checked the material master and all of the materials have MRP type P1 (MRP fix Planned Orders with the Planning time fence) and Lot size W3 (Weekly - period start).

    Thanks in advance.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      When assigning planning planning time fence in material master , system is not considering the period lot size.

      So planned order will generate after the planning time fence only.

      Beyond the planning time fence period system will consider period lot size.

      You have given MRP type P1, so planned orders inside planning time automatically firmed in that existing date & new proposal move to end of planning time fence.

      Regards,

      Dharma

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.