Error while creating PO in operation subcontracting

Former Member
0 Kudos

I am getting an Error while creating PO in operation subcontracting.When I'm trying to convert the purchase requisition for the operation in the routing into a Purchase order it gives me the error "Not possible to determine any components".Please guide me why I am getting this error. I have already assigned the component to the operation in the routing. I also have this component in stock. But no Idea why I'm getting this error

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear,

BOM should be usage 3 and the BOM should be valid for the delivery date in PO.

Check the validity date/component qty against the PO qty/Item cat in BOM/BOm usgae and come back

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks..Rajesha

Its worked..I was missing BOM usgae only...

BR

Former Member
0 Kudos

Hi Sam,

For BOM explosion in Purcahse order u have set procurement type F or X / 30 Header material.

Is it possible to in ur case ???.

What is ur routing structure, if ur subcontrating operation is last one, u can sent the raw material to ventor and receive the finished material wrt Pur order via MIGO.

If u have more oprations after the external operation, then u have to create intermaterial code with F / 30 and same to be assigned Header material BOM, in this case u cannot do operational sub contracting.

Regards

Pradeep

Former Member
0 Kudos

Hi Sam,

please check ,

Assign a recursive BOM for the material for which you want to create the purchase order .ie. create a BOM of mat say X having a component X and marking the indicator recursive ticked.

Please create the BOM which is valid much before the date of creating a purchase requisition .

And proceed for the creation of subcontract purchase requisition.

Please Revert back, if the problem is solved.

OMKAR