I am getting an Error while creating PO in operation subcontracting.When I'm trying to convert the purchase requisition for the operation in the routing into a Purchase order it gives me the error "Not possible to determine any components".Please guide me why I am getting this error. I have already assigned the component to the operation in the routing. I also have this component in stock. But no Idea why I'm getting this error

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 25, 2008 at 03:37 PM

    Dear,

    BOM should be usage 3 and the BOM should be valid for the delivery date in PO.

    Check the validity date/component qty against the PO qty/Item cat in BOM/BOm usgae and come back

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 25, 2008 at 06:19 AM

    Hi Sam,

    please check ,

    Assign a recursive BOM for the material for which you want to create the purchase order .ie. create a BOM of mat say X having a component X and marking the indicator recursive ticked.

    Please create the BOM which is valid much before the date of creating a purchase requisition .

    And proceed for the creation of subcontract purchase requisition.

    Please Revert back, if the problem is solved.

    OMKAR

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 25, 2008 at 08:58 AM

    Hi Sam,

    For BOM explosion in Purcahse order u have set procurement type F or X / 30 Header material.

    Is it possible to in ur case ???.

    What is ur routing structure, if ur subcontrating operation is last one, u can sent the raw material to ventor and receive the finished material wrt Pur order via MIGO.

    If u have more oprations after the external operation, then u have to create intermaterial code with F / 30 and same to be assigned Header material BOM, in this case u cannot do operational sub contracting.

    Regards

    Pradeep

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 29, 2008 at 02:58 AM

    Thanks..Rajesha

    Its worked..I was missing BOM usgae only...

    BR

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.