I was trying to learn how to use CMPER operation in PCR to compare for period.For a test scenario as below I am comparing For period with PP 13 and year 2017 however CMPER operation is not triggering to decision operators.

pw0xz.png (10.8 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Rémi Corriveau Nov 13, 2017 at 05:29 PM
0

It would have been nice to see the detail of the Payroll Log in order to see what Function called pcr >ZPP and wether WT 1122 was present in the Inputs, and wether WT 1122 held a value in it's Amount field.

Also, Payroll Operation AMT=AMT*2 and AMT=AMT*2 are not valid Operations. Try replacing them by AMT*2 and AMT/2.