Skip to Content

Plant Maintenance - Maintenance Plan with Multiple Counter in combination with Factory Calendar

Hi experts,

Is it possible to create a 'Multiple Counter' maintenance plan, with the option to enter a factory calendar?

For Single Maintenance Plan you can set scheduling to 'Time - factory caldr', but it doesn't seem possible for Multiple Counter plans? Is there a reason for this? For me it sounds logical to say every 1 month based on calendar, e.g. every 1st of the month. Else it starts offsetting to: first of the month, then second, etc.

Regards,

Wouter

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Nov 13, 2017 at 08:25 PM

    In addition to my Previous Answer, Paul Meehan referred to a SAP-KBA with a BAdI implementation that would suit your Needs (so all Credit to him) ...

    SAP-KBA 2549096 - Monthly key-date for multiple counter plans : link

    BAdI : "IPRM_MCP_SCHE_CHANGE"

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 13, 2017 at 10:50 AM

    Hi Wouter

    Please check the use of Cycle Counts :

    • SAP Blog "Step by Step Guide for Multiple Counter Plans" : link
    • SAP-Help "Additional Functions for Multiple Counter Plans (Master Data)" : link


    You could set one or more Cycles / Frequencies via Trx. "IP11Z" ...


    Hope this helps ...

    Nic T.

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 14, 2017 at 03:13 PM

    Thanks Nic! See you on the next SAP event perhaps :-)

    Add comment
    10|10000 characters needed characters exceeded