A change in the relevancy for materials planning is not possible

hello. I also face with this issue. Is it have any solution for it?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Nov 13, 2017 at 11:51 AM

    Sorry, but you wil need to give more information, possibly with screen-shots to illustrate your isue.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 15, 2017 at 08:20 AM

    This is from the ABAP code comments:

    Change allowed? (If the change happened during the session, change is generally possible, but the requisition must be deleted)

    Order is open (CRTD)
    Old AFVGD(DB) new AFVGD
    1 > 2 OK
    1 > 3 OK
    2 > 1 OK
    2 > 3 OK
    3 > 1 Error
    3 > 2 Error

    Order is released (REL):
    1 > 2 OK
    1 > 3 OK
    2 > 1 ERROR
    2 > 3 OK
    3 > 1 Error
    3 > 1 ERROR

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 15, 2017 at 03:19 AM

    i have tried to change Res./Purc. req. from Immediately to Never at Component Tab in IW32. But error on " A change in the relevancy for materials planning is not possible". The status automatically revert to Immediately. Is it have anything to change?

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 21, 2017 at 03:39 PM

    Two questions:

    1. What is the "Res/PReq Relevance" config setting for your plant/order type?

    2. What status is your order in when you receive this message?

    Paul