Hi,

SAP Enhancement Package 8 of SAP ERP 6.0 has been initially delivered with SP01-stack.

We would like to install it w/o installing others SP Stacks.

In the SAP Note: "2258099 - Enhancement package 8 for SAP ERP 6.0: Required SWC", it's mentioned:

"SAP Enhancement Package 8 for SAP ERP 6.0 (EHP8) is shipped as a full server load."

Does this mean that installation shipment can be installed and used without installing others stacks? (productive usage)

Thank you for your help.

Best regards,

Zobair

Accepted Solutions (1)

Accepted Solutions (1)

architectSAP
Active Contributor
0 Kudos

Hello Zobair,

You are right in that the EhP8 upgrade is different from previous EhP upgrades. This has been very well summarised by boris.rubarth:

Why EHP 8 is different

Never the less, I would still recommend that you patch to the latest FPS afterwards.

Best regards

Frank

Former Member
0 Kudos

Thank you Frank for your quick answer.

Actually business wants only to start with SPS 1.

We are not going to do an upgrade from a previous version. It's a new installation.

According to note 774615, the version of SAP_AP (SAP Application Platform) is Release: 750 SP-Level: 0000.

Is it a problem to run the level 0000?

Thank you again,

Zobair

architectSAP
Active Contributor
0 Kudos

Hello Zobair,

It is not a problem, but I would not recommend it. Patching now to the latest available FPS will save you regression testing efforts later.

Best regards

Frank

Former Member
0 Kudos

Thank you for your help,

Zobair