Skip to Content
author's profile photo Former Member
Former Member

Capacity cumulation

Hi Experts,

I have a following query:

I have to start Cpacity planning in our factory

We have four plants have same manufacturing process.

The requirement is before booking of any order on any plant sales department shuld be able to see the load on the

all the plants. then sales can decide on which plant order should be booked.

How to y out these settings in SAP

Thanks in advance,

Regards,

rajiv

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 23, 2008 at 11:35 AM

    Hi rajiv,

    Use the rough cut plan for workcenter to calculate capacity requirments for sales plan.

    To see the capacity overview for workcenter and plant sue CM01

    Rgards

    Pradeep

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 24, 2008 at 05:31 AM

    Hi Rajiv,

    Before book sale order , u have to know capacity requiremnts to produce the matreial in particular work center, as per qty in sale plan .

    Create rough cut planning for that material & plant at MC87. Inside the planning table give sale plan -> creates production plan -> and view the capacity situation for production plan.

    Before that u have to create rough cut planning profile for material & workcenter MC35.

    To view the over all capacity load of workcenter in plant use CM01,CM50.

    Please try and comeback

    Regards

    Pradeep

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi rajiv,

      I hope u have created general data for material like base qty, lotsize, bom status,usage in initila screen of rough cut plan profile -> then assign the "workcenter" of ur plant in for which u want to know capacity requirements for at "Resource table filed" (just double click.)-> assign the workcenter/plant/ unit as H (Hour.)

      also assign the produuction time value (1 hr) for teh base qty assigned in the intila screen & save.

      Now u ahve certaed rough cut plag profile for planning material & then create rough cut plan MC87. for more help plz gothrough below sap link.

      http://help.sap.com/saphelp_47x200/helpdata/en/a5/632f3b43a211d189410000e829fbbd/frameset.htm

      Regards

      Pradeep

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.