PP : Planning Strategies

Hi Gurus,

Is it possible to consider available stock in planning strategy 52? I want MRP run to consider available stock against a forecast and not to create new requirement.

I mean I have 100 pcs in stock and a forecast comes of 40 so it creates pland independent requirement. I want system not to generate any procument proposal when MRP runs. It should use available stock.

Thanks in advance.

RajaRam

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 23, 2008 at 04:01 AM

    Hi,

    Its not possible .As Planning Strategy 52 is direct production. Whenever Production Order is created automatically Order for components also created.So,it doesn't consider the available stock.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 23, 2008 at 06:06 AM

    Hi Rajaram,

    As per the planning startegy 52 (planning with out final assembly & w/o MTO) if u run the MRPafter the entry of sale order for finished material, sytem will connsider the plant avilable stock to create procurement proposal. since there is no customer stock concept. please comeback

    Regards

    Prdeep

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 24, 2008 at 07:42 AM

    Dear,

    As per the scenario, planning 74 best suits you it is almost similar to strategy 52.It is also planning without final assembly, but mixed mrp indicator = 3 indic/collector = 2 or 1. Consumption parameters, you can use consumption mode, backward/ forward .Please try and come back.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 24, 2008 at 10:39 AM

    You have not stated whether you are talking of the Final material or a component in the BOM.

    If not the BOM part then do not go for 52.

    40 or 10 are good for you.

    Also check if you have put a tick on availability check in the strategy.

    This shall give you the desired result.

    Narendra Lohokare.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 24, 2008 at 11:04 AM

    Create your own Planning Strategy similar to 52 and in the Requirement class which you have to assign to the Strategy

    select the settings as per your requirement.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks all Gurus for your invaluable time and suggestions.

      Still I can't get the solution I want. I have following situation:

      Date MRP element Req. Qty Available

      25.01.2008 Stock 200 200

      25.01.2008 -


      > Planning without assembly 0 0

      01.02.2008 PldOrd 0000108425/INDR 100 100 2001

      01.02.2008 IndReq ZVSE 100- 0

      03.03.2008 PldOrd 0000108426/INDR 100 100 2001

      03.03.2008 IndReq ZVSE 100- 0

      As we have got a stock I don't want system to create any requirement.

      This happens with strategy 52 because we can't control anything below this line

      "25.01.2008 -


      >Planning without assembly"

      please give me the solution.

      RajaRam

  • author's profile photo Former Member
    Former Member
    Posted on Jan 24, 2008 at 08:55 PM

    Dear,

    I am trying to understand your requirement,

    If you feel that stock has to be consumed first against the PIR(forecast), then why not simple stg 40 cannotb be cosidered. In 52, we just plan the components early stage hence PIR is to be created and planned order has to be created weel in advance. That too when the sales order is received, it will knockoff the planned order created.

    Hence if you keep the planned order open till you get the concreate sale order...it will also serve the same purpose.

    Kindly let us know your business requirement...it is very intersting..for which industry youare working and the what is the business requirement...

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.