plant calendar vs. shipping calendar

Former Member
0 Kudos

Dear gurus,

I am struggling with calculation of transportation time to be considered following:

1. I need to have 5 days working calendar to be able to have picking, loading only on workdays

2. for the calculation of loading (picking) date, I need to consider also non working days. We have got the routing that calculates from the delivery date by customer the loading date.

Can you please help me how to manage it?

Many thanks in advance

BR, David

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Problem solved. We set plant calendar in route determination.