Skip to Content
avatar image
Former Member

how to derive settlement rule for wbs element from cost center

hi everyone:

how to derive settlement rule for WBS element from request cost center or responsible cost center . because I didnot find settlement rule in cost center master data. thank you

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jan 22, 2008 at 04:25 PM

    I can get your question right, you want the settlement rules to be automatically created with Req Cost Center or Rep Cost Center (as on the WBS master data) as receiver objects.

    Below are the steps:

    1. Maintain a Settlement profile where Cost Center is Valid Receiver object

    2. Maintain the node 'Determine Strategy for Settlement Rule' . In the setting mention the required strategy, settlement profile created above and account assignment category as '2'/'3' - Your case.

    3. Assign the Strategy Sequence 'SAP030' or 'SAP040' in your case on the settlement parameters of the WBS.

    4. Execute T code CJB2/CJB1

    Regards

    Sreenivas

    Pls close the post if satisfied.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 23, 2008 at 07:06 AM

    Hi,

    You need to maintain the settlement rule in WBS Element. For this go to CJ20N select the WBS Element then Edit ->Costs -> Settlement rule. Here you can maintain the rule with the receiver as cost centre.

    Hope this helps.

    Regards

    Sreekanth

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 03, 2008 at 12:06 PM

    Can you please close this post if the issue is resolved?

    Regards

    Sreenivas

    Add comment
    10|10000 characters needed characters exceeded