I am extending a material without QM view but the QM procurement Key is taking by default.

I am not able to see the the QM procurement key in material master but table level it is displaying .

Could you please suggest some what the setting to pick the default control key without extending the QM view .

Thanks in advance.

Regards

Arabind

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Jürgen L
Nov 09, 2017 at 02:02 PM
0

About what field you are actually talking

QM in procurement active? this is a MARA field (MARA-QMPUR), even it is located in the QM view, if one plant has made this entry then it is present for any other plant to which the material is to be extended.

Or are you taking about QM control key (MARC-SSQSS)? This control key is not defaulted in standard, if this is the case in your system then it is probably done with a BADI, ask your local IT.

Show 3 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hello Jurgen,

Thanks for quick response

The field is MARC-SSQSS .When creating a new material for a plant then by default this field value is updating in the MARC-SSQSS field without extension of QM view .

Regards

Arabind

0

I already answered about this situation above. It is not standard and if this is the case in your system then talk with your local IT department as they may have applied a modification based on your very local design requirements.

If you have no modification/user exit in place then please use transaction ANST to check again and to see if there are any bug fixes to be applied.

and if nothing about exits/modification or proposed OSS notes comes up then you may report a bug to SAP Support.

0
Former Member

Thanks Jurgen, I will check and get back to you.

Regards

Arabind