Hi Gurus,
We are not getting the scrap/ variance in cost analysis plan/ actual comparison inside production order even we are posting scrap in production order confirmation and doing variance calculation. Where to give the settings in order to achieve this.
Edited by: Rijil Raj on Jan 26, 2008 7:13 AM
I got the solution. Target version was not assigned in variance run.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
post the scrap using movt type 531 (posting with reference to production order) this will update the scrap cost into the prdn order
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
for this you have to define ur cost sheet where in that you have to define the costing variant and valuation vaiant
but this setting you have to do with ur fi co person.
reward points if useful to you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your reply.FiCo person has set the costing variant and valuation variant. Also we have created variance key and variance variant in controlling. still the scrap/variance is not comming in production order after variance calculation. could you just specify which setting is missing in costing sheet.