on 01-22-2008 10:28 AM
Morning All
On solution manager, when it says that the leading role of the solution created is Production, what does it mean?
Is it possible to change the leading role of the solution to Development after you have created the solution and how is this done?
It seems like for every business scenario I am trying to create, the logical components ae pointing to Production system and I want to do my tests on Development as I cannot test on production. I do not know on whether this is because of the leading role of the solution being Production.
Regards
Khuselwa Mabandla
Hi,
"Changing the Leading Role must be the very first step when maintaining the Solution Directory. Once you have changed anything else in the Solution Directory (or via work center “SAP Solution Manager Administration”), for example assigning a Logical Component, a Business Scenario, etc., it will be no longer possible to change the Leading Role."-BPMon SetUp Guide
regards,
Jai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Khuselwa,
if you are in SOLAR01 you can go to Business Blueprint > System Role and change it there. Now all the logical components point to the role you selected.
regards,
Jason
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.