In make to order cycle semifinished costs are not appearing in itemisation

Former Member
0 Kudos

Hi

We are facing a problem in Make to order. When a production order is created with respect to a sales order, semifinished costs are not appearing in Itemisation or cost component structure of Production order.

In other cases like make to stock and planning with final assembly costs are appearing. we are checking costs at CO02 - goto menu- costs - itemization.

Please provide us solution for this problem.

Thanks and regards,

Deepa

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Please check 'Cost component Structure' Attribute details data for the semifinished component.

In that chek for 'Rollup cost' and also check for 'Filter Criteria for cost component views on Itemization' properly.

Regards

Laxmiprasad

Apart from above pls check for semifinished product in material master in costing1 view for material origin check box, check it if not selected.

Regards

Laxmiprasad

Edited by: Laxmiprasad Pagidala on Jan 22, 2008 2:03 PM

Former Member
0 Kudos

Hi Deepa,

Please try the following:

1. Check the cost component structure again in 'OKTZ', whether you have considered all the cost elements relating to HALBs or not.

2. Check with the PP consultant for BOM structure.

Former Member
0 Kudos

Hi,

I gave the cost elements in Cost component structure.

Costs are flowing in make to stock strategy, but these are not appering in make to order scenario.

Thanks for your response,