on 01-22-2008 6:22 AM
Hi
We are facing a problem in Make to order. When a production order is created with respect to a sales order, semifinished costs are not appearing in Itemisation or cost component structure of Production order.
In other cases like make to stock and planning with final assembly costs are appearing. we are checking costs at CO02 - goto menu- costs - itemization.
Please provide us solution for this problem.
Thanks and regards,
Deepa
Hi
Please check 'Cost component Structure' Attribute details data for the semifinished component.
In that chek for 'Rollup cost' and also check for 'Filter Criteria for cost component views on Itemization' properly.
Regards
Laxmiprasad
Apart from above pls check for semifinished product in material master in costing1 view for material origin check box, check it if not selected.
Regards
Laxmiprasad
Edited by: Laxmiprasad Pagidala on Jan 22, 2008 2:03 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deepa,
Please try the following:
1. Check the cost component structure again in 'OKTZ', whether you have considered all the cost elements relating to HALBs or not.
2. Check with the PP consultant for BOM structure.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.