MIGRATION FROM SAP PI 7.1 and 7.3 TO SAP PO 7.5

Dear Experts,

Please share step by step by process of migrating PI 7.1&7.3 dual stack to single stack tools and procedure as am new to PI.

Thanks

Sai

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Dec 16, 2017 at 10:23 AM

    Hi Sai,

    The detailed steps as follows:

    1.Install new PRO system running side-by-side to existing PI dual stack system

    2.Sync SLDs

    3.Transport of Enterprise Services Repository objects

    4.Migrate Integration Directory objects using migration tool

    5.Redesign of ABAP based artifacts (ABAP mappings, ccBPM processes, etc.) in PRO system

    6.Setup new message based alerting

    For the step 4 migration, please check the following links in details:

    http://help.sap.com/saphelp_nw74/helpdata/en/7e/717ce013624facafa76683099a56d5/content.htm

    http://scn.sap.com/community/process-orchestration/blog/2012/11/19/moving-integration-directory-artifacts-from-dual-stack-to-single-stack

    http://scn.sap.com/docs/DOC-46713

    Regards,

    Liz

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.