Hello everyone,

can we do the planning and budgeting @ storage location level under a plant?

Can we create a release strategy using a cost centre as a characteristic?

Thanks in advance

Regards

Sachin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Cost planning and Budgeting cannot be done at Storage location level.

Budgeting can be done only at WBS level.

regards

Pratap.V

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can make each storage locations as WBSE in order to make cost planning / budgeting in your project. You need to frame the project structure.

Regards,

Rakesh Pradhan