How to change company code in Assignment tab (CJ20n-project builder)

Dear All,

Is there any config to maintain company code in assignment tab (project builder) ? We have a problem in our project. It shows that in basic data, user put company code A (in basic data) but in Assignment tab they put different company code let say B. When we do settlement , two accounting document created to company code A and B. By right it should be only company code A. In addition, we cannot change the company code, when the status is already Release (REL).

Please help how to change the company code B to A and how to reverse the accounting document that has been created under these two accounting document.

Thank you.

Best Regards,

nies

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jan 21, 2008 at 10:26 AM

    Not clear about your question here. Do you mean to say that you see field company code on both the Standard Tabs i.e., Basic data and Assignments? I think it's not possible to have the same field (PBUKR-Company code) with different values on a WBS.

    You can not even revoke the REL status on the WBS.

    Coming to reversal, you can still reverse the settlement entries (but again this would generate some FI/CO documents) using CJ88. Choose from Menu Settlement->Reverse.

    Regards

    Sreenivas

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Now I understand your scenario, you have the Requesting Company Code and the Company Code Different.

      You usually use this primarily with IM module if you want to manage the asset under construction (cross company) belonging to a different i.e., company code (Requesting ) than company code on main WBS.

      You can not change the company code (Assignment Tab) as you already have actual posted against it.

      You've also created an AUC (in wrong company code) and even if you reverse the settlement you would not be allowed to delete the AUC or the delete the settlement rule (its grey out as its already used)

      What I can suggest is to reverse the settlement, lock this WBS which was created wrongly, create a new WBS and then continue with you regular process.

      Above are my views but you can expect views from others.

      Regards

      Sreenivas

      Please close the post if satisfied.