Confirmation of Activity with still work remaining.

Hello Friends,

I have an activity say Internal assigned to a WBS element. I have attached, material component’s three (3) , one has Purchase Requisition + reservation for WBS, and others materials are reservation for networks.

Stock of all the materials is Nil (Zero). Purchase Requisition is generated while releasing the activity. Still the activity is not fully completed.

If I try to “CONFIRM “ the activity the system allows me to do the same, i.e. final confirmation, even the PO is release and GR done, other materials stock is not increased etc.,. I would like to link such that a warning or error should occur during confirmation “ saying the activity is not completed”. How we can do the same.

RamananPV

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jan 21, 2008 at 04:34 AM

    Hi,

    The functionality which you are looking for (Automatic confirmation of activity) may n't possible in standard SAP. To confirm the activity, you need to confirm through transaction CN25 / CN27. In order to make automatic confirmation on procurement, you need got for developments.

    Hope this will help you.

    Regards,

    Rakesh Pradhan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      System will allow confirmation of activity irrespective of release of PO / GI etc. There is partial confirmation of activity also. Morever there is no logic of material procurement w.r.t. activity confrimation as system won't identify completion of procurement process. Confirmation of activity is based on user only.

      Hope this will help you.

      Regards,