on 01-20-2008 6:52 AM
Dear all,
During matl master creation whether we need to give any price for S or V ?
what is the use of this ?
Because when we run cost estimate in CK40N the given value become previous price.
I tried the value of inhouse product the new value is higher that old value
Pl carify this.
guru
you need not give the price for product. nut you need to give it to all raw material. For the product/sub assembly we can calculate the same through CK24 (standard cost estimation) and update the material price.
Edited by: Rajesha Vittal on Jan 20, 2008 8:12 AM