PR issue

19 Views

HI

1.once after raising a PO for complete qty with ref to PR, system should automatically set check box "Close" under item level qty/updates tab ( If i am correct), but in my case though i created PO for full qty system did not checked that box for the ref PR.

Any possible reasons in SAP why system did ot update Close check box in PR?

2. Even after creating PO system did not updated the PO no in MD04 system not showing the PO no for the corresponding PR why?

Then i went into ME52n and ckecked that tick box then it got removed from MD04.

Now user is asking above two questions.

I am from SD module, pl address me and clarify me if i am wrong.

Reg

shan1242