BOM dates

Hi All

I need to create a BOM that contains different materials depending of what date it is. I.e. the BOM changes from a specific date. Does anyone know how this is set up?

/ Henrik

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jan 18, 2008 at 03:07 PM

    Hi Henrik,

    If you want MRP to explode your BOMs according to date you can define this:

    SAP menu > Logistics > Production > MRP > BOM by Date (OPPP)

    http://help.sap.com/saphelp_46c/helpdata/en/f4/7d2aea44af11d182b40000e829fbfe/frameset.htm

    BR

    Csaba

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 18, 2008 at 03:40 PM

    hi,

    are you referring to a sales BOM or production BOM. However in case a sales BOM while creating the BOM maintian the required components into it with the required validity dates. So when you create a sales order automatically those components which match the specified date criteria are exploded and not the ones which are out of validity.

    regards