on 01-18-2008 2:16 PM
Hi experts,
I would like to know if its possible set in the Customizing, the Commitment just for Purchase Order.
Because, currently we have fixed Purchase Requisition and Purchase Order.
Thanks in advance.
Nacho
Hi,
In SPRO settings under Project System.Costs>Budget-->Define tolerance limits-Project Avaliability control assign activity groups 00 and 01 to the budget profile which is assgned to Project Definition.
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks very much. It works.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
SAP Note:955107 addresses this problem. You may refer the note, but for easy reference, relevant portios of the note are quoted below:
Quote begins:
Symptom
The purchase requisition commitment should not be taken into account in the availability control.
How can this be achieved?
Reason and Prerequisites
This is a customer request.
It should be possible to enter purchase requisitions with any amount and only the resulting purchase orders should be checked by an availability control.
Solution
For Releases 4.6C, 4.70, 5.00 and 6.00 first implement the corrections from Note 955106 if you have not already done this.
Afterwards proceed as follows.
1. Create a utility program ZBPFCI21 of the 'Subroutine Pool' type. For the source code of the program refer to the attached correction instruction 488705.
Caution: Do not use a different name than ZBPFCI21.
2. Adjust the source code within the utility program ZBPFCI21 as follows:
When the residual order plan should not be included in the assigned value of the availability control, activate the line
CLEAR cd_flag_pr_commitment_avac.
(That is, delete the sign '*' in front of the line.)
3. Save and activate the ZBPFCI21 utility program.
4. Reconstruct the assigned values of the availability control (Transactions KO31 for orders or CJBN for projects).
Quote ends.
Kindly acknowledge, if it meets your requirement.
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.