Hi,

When i am creating sales order(service item), it is automatically picking up wbs element after saving the sales order.

The number for wbs element is just like sales order, no. It is copying standard project and wbs for this

My question is what is the link between these

where i can see the defaults settings for automatic picking of wbs element

regards

chidambaram

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

The material is assigned to a standard network in CN08 and while creating order for the material and saving the order a project is created in PS with the same sales order number.

Go to CN08 and check.

Reward points if useful.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Goto t-code CJ03 and give WBS element you have it in the sales order and then enter.

Select the line item of WBS and then lick "Shift+F1" and there you clcik "control data" view and then see under Sales pricng.

here they may mentioned Sales area.

Let me know if it is OK.

Regards,

Chandra

Former Member
0 Kudos

Hi,

This is triggaring from Project System u can check with ps consultant.