Hi Gurus,

Greetings.

I am encountering problems in delta report(/n/sapapo/ccr). I cannot reconcile the error nor sendig to APO does not

correct error 173. Difference in confirmation status o R3 against APO.

I checked the process order in r3 it is alreay delivered- with final confirmation against APO with release

status.

Kindly help if someone has already encountered th same problem.

Thanks

Armi

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 28, 2008 at 09:26 AM

    Hi Armi,

    We have encountered the same problem. In our system, the cause why it can't be reconciled via Delta REport is the changes made to the master data. The routing for the material is changed in our scenario.

    The inconsistency can be rectified by putting the order in Status TECO.

    Hopes this helps,

    Raymond

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 30, 2008 at 10:09 AM

    Hi Raymond,

    Thanks for the inputs. It definitely resolve our issue.

    Regards,

    Armi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.