How i can maintain WBS Element variences in SAP

Dear Friend's

How i can maintain WBS Element variences in SAP ( Example: if their is 10 activities in wbs element which is to be completed within a Six Month duration, but only 5 activities are completed in Six Month & remaining are pending which may carry for next Three Months.So i want to maintain this plan vs actual variance with reason's )

How i can do in sap.

WBS Element - Plan - Actual - Variance - Reason

Civil Work - 10 activities - 5 activities - 5 activities - matrl shortages & insufficient fund

Regard's

Sandeep

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jan 21, 2008 at 01:43 AM

    Use Statistical Key Figures for this:

    KK01 - Create SKF's (activities like Nos. of Drawings etc.,)

    CJS2 - Change (WBS Element) *Plan SKF's against the WBS

    KB31N - Enter *Post the SKF's

    S_ALR_87013548 - Statistical Key Figures/Periods * View Plan/Actual/Variance of SKF

    You can enter Text's while posting the SKF's in transaction KB31N but I'm not sure about how this can be pulled into the report.

    Regards

    Sreenivas

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Try below transaction:

      GR5G - Generate

      Generate the report group 6PP7 and check if report was successfully generated.

      Regards